Skip to content
tew-services

Technical project design & delivery

End-to-end engineering solutions for complex projects in public and private sectors, including manufacturing, water, transport, construction, commercial buildings and industrial.

Electrical and mechanical design expertise for demanding engineering applications

In-house facilities for pre-construction project equipment manufacturing and sub-assembly

Electrical and mechanical equipment installation and related civil and construction works.
Proactive asset maintenance, repair, refurbishment and upgrades.

Qualified expertise in project work for hazardous areas and high voltage applications.

Multidiscipline engineering projects with complex scope, scale and technical requirements.
Whatever the industry, TEW brings its combination of agile thinking and high-level expertise.
TEW-Urban-Turf-04

Artificial Turf Backing Line Relocation, Gold Coast

LocationOrmeau, Gold Coast
Client/s

 — Urban Turf

Value$240K

 

Project Scope

TEW was engaged by UTS to undertake the relocation of a one of a kind backing line used in the textiles manufacturing process.

  • Design and construct
  • Relocation of existing production equipment.
  • Undertake modifications of process plant including extensions for increased quality inspections, additional cooling and minimising downtime.

 

TEW-Urban-Turf-05

 

Challenges

  • Critical timeframes and changeovers during Christmas Shutdown.
  • Transport of specialist and unique production plant and equipment.
  • Undertaking modification of an existing process and implementing in new premises once existing plant and equipment relocated.
  • Relocating electrical infrastructure with no existing electrical drawings or schematics.
  • Critical handover of knowledge within delivery team due to planned/scheduled holidays.

 

Outcomes

  • Successful relocation of existing plant and equipment.
  • Successful implementation of modified process.
  • Met timeframes and allowed plant and equipment to commence production once client workforce returned from Christmas shutdown.
  • Documented electrical infrastructure.
  • Undertook 3D scan of existing plant and equipment at existing premises. Integrated new process within existing plant and equipment. Undertook 3D scan at new premises and integrated layout prior to planned shutdown to ensure correct layout and review possible clashes.

 