Project Scope
- Construct with design responsibilities
- E&I detailed design, procurement, installation, test and commissioning of Mechanical and Process equipment.
- Detailed design, fabrication and delivery including installation of Main Switchboard, Motor Control Centre and various PLC and Network enclosures.
- Supply authority liaison including supply of authorised workers.
- Site delivery across Two (2) Treatment Plants including integration with existing functioning Treatment Plant Power and Control System.
- Arc flash and AS 61439 compliance.
Challenges
- Existing building constraints impacting on new Electrical Infrastructure.
- Interfacing with multiple stakeholders delivering adjacent works.
- Interfacing with existing electrical infrastructure within an existing operational Waste Water Treatment Plant.
- Design deviations during project installation works.
- Expedited project delivery.
- Extended delivery lead times due to supply chain impacts.
Outcomes
- Successful design, construction and installation of Electrical Infrastructure within existing Building envelope.
- Successful alignment with key stakeholders to assist with expedited project delivery.
- Successful integration with existing Power and Control Systems.
- Successful detailed design and alignment with various overarching technical specifications (end Client and Supply Authority).